Location
Kurri Kurri, New South Wales
The overall project involved the design and construction of seven separate crossings, totaling to 5.9 kilometres of 14-inch steel pipe installed that ultimately assisted in tying in the gas transmission line from the Sydney to Newcastle pipeline (Plumpton to Hexham Northern Trunk) to the Hunter Power Project. Utilising HDD as the installation methodology allowed the pipeline to pass underneath several creeks, roads, sensitive flora and fauna zones and cultural heritage areas whilst ensuring that these sensitive environments remained undisturbed.
UEA was engaged by Spiecapag Australia as the sole HDD contractor to deliver this multi rig project consisting of seven separate crossings. The total length installed via HDD was 5.9 kilometres, with the individual bore lengths ranging from 400 metres to 1,230 metres, and two of the respective bores included a drilled mud return line in addition to the main line. A combination of a Herrenknecht 250C, a Vermeer D330 and a Vermeer D300 were utilised across the two HDD crews to seamlessly execute this technically challenging project.
In collaboration with Future-Proof Solutions, both parties brought APA Group’s concept designs to fruition, successfully delivering seven compliant profile and alignments and associated calculation documentation.
Highside Drilling were engaged as the designated steering subcontractor with a combination of Partarack 2 and Gyro deployed across the project as the designated method of tracking, in order to ensure all pilots were accurately steered in accordance with the design.